Around the Front Door cannot be finished yet as the Door Frame needs to be replaced as it is warped from laying in the rain, should be done next week.
Sunday, February 10, 2008
Sh!t a Brick
Saturday, February 9, 2008
Slow and Steady Wins the Race.
The Chippy was back this week also to bolt the frame down and the glaziers were in to put glass into the bi-fold doors.
Wednesday, January 30, 2008
We're Wrapped
Saturday, January 26, 2008
We have Plumbing, Tiles and Bricks
The Tiling started on Tuesday.
And by Friday it was finished.

Oh and this is my new Company Car ( pity it's a Ford )
Friday afternoon the Bricks were delivered
Next week should be the insulation wrapping and the electrical starting. The bricking may be a couple of weeks away due to lack of Brickies.
Saturday, January 19, 2008
Well were Guttered
Thursday, January 17, 2008
Finally looking like a House
Before Christmas we had a few hold ups, firstly the one of the guys shot himself in the knee with his nail gun 'OUCH'. Then the wrong trusses were delivered. After a rocket you know where on Monday it was all guns blazing with extra guys on site to finish the framing.



The view from the bridge over the wetlands.
Here is our Alfresco and Bi-Fold Doors.
Looking from the Family Room to the Front Door.

Looking from the Kitchen to the Family room.

The Front Entry.
The Dining Room.

The Gutters and Fascia should be up tomorrow, and the Roof Tiling started next week.
Sunday, December 16, 2007
I've got wood

Then the front door frame and the temporary front door.
Here is our front door and handle, it will be installed closer to handover so some nice person with light fingers doesn't borrow it.
The 'Chippies' then marked on the slab where the rooms will be.
And cut and laid the timber out to start building the frame.
It was really good to finally see the rooms where everything will be.

More work tommorow hopefully, according to our Supervisor the gutters and fascia will be on by Christmas. Better get moving boys.